Old Main Under Construction


Exterior

Renovations to the stucco and french drains
began in 1999 and finished in 2001.
Cost: $600,000




Central Campus HVAC
Loop System

The creation of a new central campus heating,
ventilation and air conditioning system looping
Main Building, Shipp Hall and DuPré Hall
was completed in 2001.
Cost: $1.2 million
Old Main 2 
West Wing
April 2005 to February 2006 saw renovations to the West Wing classrooms
and faculty offices. Accessibility includes an
elevator with ground level access in this wing. Also completed during this phase was the renovation of Mickel Chapel.
Cost: $1.7 million

 
Leonard Auditorium
The auditorium has state-of-the-art sound, AV movie screen, lights and
controls. Renovations were completed
during the summer of 2006.
Cost: $3.2 million
Blueprints of Old Main  East Wing
Between February 2005 and November 2006,
East Wing faculty offices and classrooms underwent a major renovation.
Cost: $2.2 million